Airport works description:

 

  1. Received Technical information included Building services dwgs from Airport Authority.

  2. Issued Initial MVAC Design Drawings c/w Loading calculations for AA Approval.

  3. Submitted Material for approval

  4. Ordered and delivered material to site once got the work permit from AA.

  5. PICV ( Pressure independent control valve ) is a must equipment to all sites and the model and controlled chiller water Flow are subject to AA approval before ordered and delivered

  6. Perform T&C after MVAC work completed and submitted the final report to AA for Record and final approval.